Current state
| Status | Under construction |
| Design | BWRX-300 (BWR, SMR) |
| Net capacity | 300 MWe |
| Country | Canada |
| Vendor | GE Hitachi (GE Vernova) |
| Owner / operator | Ontario Power Generation |
| Construction start | 2025 |
| Original COD target | 2030 |
| Current COD estimate | 2030 |
| Schedule slippage | 0 years |
Notes
First grid-scale SMR construction in the West; the FOAK cost/schedule benchmark for the entire BWRX-300 order book (Poland, TVA, SK).
Milestone log
- 2025-04-04 — CNSC licence to construct granted; OPG/Ontario approved ~C$20.9bn for four units (source)
- 2026-06-24 — OPG applied to CNSC for 20-year operating licence — would be first operating SMR in a G7 country (source)
- 2026-07-01 — Unit 1 reactor building shaft excavation past 80%; reactor pressure vessel in manufacturing (source)
The milestone log is append-only: corrections are recorded as new entries, never rewrites. Full history via /api/v1/changes.