Hinkley Point C-1

EPR · 1,630 MWe · Under construction · commercial operation est. 2030

Current state

StatusUnder construction
DesignEPR (PWR)
Net capacity1,630 MWe
CountryUnited Kingdom
VendorEDF/Framatome
Owner / operatorNNB Generation Company (EDF)
Construction start2018-12-11
Original COD target2025
Current COD estimate2030
Schedule slippage+5 years

Britain's first new nuclear plant in a generation and the benchmark for Western large-reactor construction economics.

Notes

Flagship Western new-build and the canonical slippage story: 2030 start-up is five years past the original 2025 target. Unit 1 civils 94% by concrete volume at end-2025.

Milestone log

  • 2018-12-11First nuclear concrete poured (official construction start) (source)
  • 2024-01-23EDF announced revised schedule (Unit 1 2029-2031) and cost range £31-35bn (2015 money) (source)
  • 2026-01-20All 24 primary loop welds completed on Unit 1 (source)
  • 2026-03-02Unit 1 start-up pushed to 2030 on M&E productivity shortfall; cost estimate £35bn (2015 money) (source)

The milestone log is append-only: corrections are recorded as new entries, never rewrites. Full history via /api/v1/changes.