Kudankulam-3

VVER-1000 · 917 MWe · Commissioning · commercial operation est. 2027

Current state

StatusCommissioning
DesignVVER-1000 (PWR)
Net capacity917 MWe
CountryIndia
VendorRosatom
Owner / operatorNuclear Power Corporation of India (NPCIL)
Construction start2017-06-29
Original COD target2023
Current COD estimate2027
Schedule slippage+4 years

Notes

Reactor-stage commissioning underway; plant director targets 2026 commissioning, commercial operation conservatively 2027. Units 4-6 need separate entries.

Milestone log

  • 2017-06-29First concrete, Unit 3 (source)
  • 2025-12-10First fuel batches delivered to site for Unit 3 (source)
  • 2026-04-25'Spill to open reactor' commissioning milestone reached (source)

The milestone log is append-only: corrections are recorded as new entries, never rewrites. Full history via /api/v1/changes.